Agenda:
Progress to date.
Ways to Proceed.
Version 01: Rhythm
1.1, 2021-Nov: profit reconciliation and data issues such as PS costs, direct construction costs,etc.
1.2, 2021-Dec: discussion and solving data issues
1.3, 2022-Jan: static data version is created for Rhythm, and financing is built in specifically for this project.
1.4, generally: total budget/deposit/financing interaction is not quite clear.
Version 02: Parkview
2.1, 2022-Jan: polishing up financing, but the budget/deposit interaction has issues: assumption is 5% *( total budget-deposit)
2.2, generally: Lots have been focused on reconciling total cash flow with total profit
Version 03: Creekside
3.1, 2022-Jun: dynamic deposit, standard financing for HB, manual lines for costs and financing
3.2, to date: finish HB.
Version 04: Rhythm
4.1, 2022-Jul: Integrate HB financing to creekside
4.2, 2022-Aug: Build in Land cash flow
Version 05: Mer Blue
5.1, 2022-Sep: Integrate HB financing to rhythm
5.2, 2022-Oct: Build in land cash flow
OTT Land: land CF that has existing HB CF
1.1, 7 projects: OTL300,OTL400,OTL404,OTL406,OTL500,OTL505,OTL506,
OTT Land: land cash flow under new template
2.1, 10 projects: OTL302, OTL303, OTL305, OTL402, OTL405, OTL501, OTL504, OTL601, OTL602, OTL603
Single phase model requirement: switch from financial to operational model
multi-phase data integration, but the logic needs to be clarified
some feedback from Ottawa division team: too many excels lead to crash, a choice between excel and database as source.