Changes in PJM Queue between July 12th, 2021 and July 26th, 2021.

Where an existing project has some updated field, you’ll find two rows for that project, with the new entry on top, updated fields highlighted in green, and deprecated fields highlighted in red in the bottom row.

Fully new queue positions appear as individual rows with all fields highlighted green.

Summary of Changes

##   old_obs   new_obs   changes additions  removals 
##      7440      7454        69        14         0

Changes

## Creating HTML table for first ${limit_html} rows
QueueNumber chng_type Name CommercialName State County Status TransmissionOwner MaximumFacilityOutput MWEnergy MWCapacity MWInService CapacityorEnergy ProjectType Fuel ProjectACOrDC RightsMW InitialStudy FeasibilityStudy FeasibilityStudyStatus SystemImpactStudy SystemImpactStudyStatus FacilitiesStudy FacilitiesStudyStatus InterimInterconnectionServiceAgreement InterimInterconnectionServiceAgreementStatus WholesaleMarketParticipationAgreement ConstructionServiceAgreement ConstructionServiceAgreementStatus UpgradeConstructionServiceAgreement UpgradeConstructionServiceAgreementStatus BackfeedDate QueueDate LongTermFirmServiceStartDate LongTermFirmServiceEndDate TestEnergyDate WithdrawalDate WithdrawnRemarks ProjectedInServiceDate RevisedInServiceDate ActualInServiceDate SuspensionDate AttachmentType AlternateQueue SlideQueue
AB2-031 + Brink-Trego 115kV Meherrin Solar VA Greensville Under Construction Dominion 59.6 20 13.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2031_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2031_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ab2031_fac.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/isa/ab2_031_isa.pdf Document Posted N/A https://www.pjm.com/pub/planning/project-queues/csa/ab2_031_csa.pdf Document Posted N/A N/A 2/11/2016 N/A N/A 1/1/2022 4/1/2022 4/1/2022 N/A N No
AB2-031 - Brink-Trego 115kV Meherrin Solar VA Greensville Under Construction Dominion 59.6 20 13.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2031_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2031_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ab2031_fac.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/isa/ab2_031_isa.pdf Document Posted N/A Not Required N/A N/A 2/11/2016 N/A N/A 1/1/2022 4/1/2022 4/1/2022 N/A N No
AC1-001 + Delano 138kV OH Ross Active AEP 49.9 49.9 33.93 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1001_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1001_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ac1001_fac.pdf Document Posted N/A N/A 5/5/2016 N/A N/A 10/31/2017 N/A N No
AC1-001 - Delano 138kV OH Ross Active AEP 49.9 49.9 33.93 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1001_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1001_imp.pdf Document Posted In Progress N/A N/A 5/5/2016 N/A N/A 10/31/2017 N/A N No
AD1-068 + Albright-Garrett 138 kV WV Preston Withdrawn APS 80 80 11.76 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1068_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1068_imp.pdf Document Posted Withdrawn N/A N/A 8/31/2017 N/A N/A 7/19/2021 12/15/2020 N/A N No
AD1-068 - Albright-Garrett 138 kV WV Preston Active APS 80 80 11.76 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1068_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1068_imp.pdf Document Posted In Progress N/A N/A 8/31/2017 N/A N/A 12/15/2020 N/A N No
AD1-140 + Greene-Clark 138 kV OH Greene Active ATSI 175 175 95.8 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1140_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1140_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ad1140_fac.pdf Document Posted N/A N/A 9/29/2017 N/A N/A 5/29/2020 N/A N No
AD1-140 - Greene-Clark 138 kV OH Greene Active ATSI 175 175 95.8 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1140_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1140_imp.pdf Document Posted In Progress N/A N/A 9/29/2017 N/A N/A 5/29/2020 N/A N No
AD2-009 + McConnellsburg 138 kV PA Fulton Active APS 70 70 48.1 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2009_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2009_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ad2009_fac.pdf Document Posted N/A N/A 11/3/2017 N/A N/A 6/30/2019 N/A N No
AD2-009 - McConnellsburg 138 kV PA Fulton Active APS 70 70 48.1 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2009_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2009_imp.pdf Document Posted In Progress N/A N/A 11/3/2017 N/A N/A 6/30/2019 N/A N No
AD2-134 + Shady Oaks IL Lee Active ComEd 217.8 108.33 21.7 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2134_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2134_imp.pdf Document Posted In Progress https://www.pjm.com/pub/planning/project-queues/isa/ad2_134_isa2.pdf Interim Study N/A https://www.pjm.com/pub/planning/project-queues/csa/ad2_134_csa.pdf Document Posted N/A N/A 3/23/2018 N/A N/A 10/31/2021 10/31/2021 N/A N No
AD2-134 - Shady Oaks IL Lee Active ComEd 217.8 108.33 21.7 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2134_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2134_imp.pdf Document Posted In Progress N/A N/A 3/23/2018 N/A N/A 10/31/2021 10/31/2021 N/A N No
AE1-129 + Zion View - Middletown 115 kV Strinestown Solar Project PA York Engineering and Procurement ME 79.6 79.6 47 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1129_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1129_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae1129_fac.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/isa/ae1_129_isa.pdf Document Posted N/A https://www.pjm.com/pub/planning/project-queues/csa/ae1_129_csa Document Posted N/A N/A 9/7/2018 N/A N/A 12/31/2023 12/31/2023 N/A N No
AE1-129 - Zion View - Middletown 115 kV PA York Active ME 79.6 79.6 47 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1129_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1129_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae1129_fac.pdf Document Posted N/A N/A 9/7/2018 N/A N/A 9/30/2021 N/A N No
AE1-196 + Hokes-Jackson 69 kV II PA York Active ME 20 20 12.6 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1196_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1196_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae1196_fac.pdf Document Posted N/A N/A 9/26/2018 N/A N/A 4/1/2021 N/A N No
AE1-196 - Hokes-Jackson 69 kV II PA York Active ME 20 20 12.6 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae1196_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae1196_imp.pdf Document Posted In Progress N/A N/A 9/26/2018 N/A N/A 4/1/2021 N/A N No
AE2-042 + Milton 69 kV Northumberland Solar PA Northumberland Engineering and Procurement PPL 70 70 46.8 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2042_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2042_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae2042_fac.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/isa/ae2042_isa.pdf Document Posted N/A https://www.pjm.com/pub/planning/project-queues/csa/ae2042_csa.pdf Document Posted N/A N/A 1/23/2019 N/A N/A 3/24/2023 3/24/2023 N/A N No
AE2-042 - Milton 69 kV PA Northumberland Active PPL 70 70 46.8 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2042_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2042_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae2042_fac.pdf Document Posted N/A N/A 1/23/2019 N/A N/A 6/30/2022 N/A N No
AE2-082 + Englishtown-Wyckoff 34.5 kV Solar NJ Monmouth Withdrawn JCPL 7 7 3.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2082_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2082_imp.pdf Document Posted Withdrawn N/A Withdrawn N/A N/A 1/31/2019 N/A N/A 7/13/2021 9/30/2019 N/A N No
AE2-082 - Englishtown-Wyckoff 34.5 kV Solar NJ Monmouth Active JCPL 7 7 3.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2082_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2082_imp.pdf Document Posted N/A N/A 1/31/2019 N/A N/A 9/30/2019 N/A N No
AE2-148 + Beatty-Greene 345 kV OH Madison Active AEP 577 577 397.3 Capacity Generation Interconnection Solar; Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2148_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2148_imp.pdf Document Posted In Progress Not Required N/A N/A 2/20/2019 N/A N/A 6/1/2022 N/A N No
AE2-148 - Beatty-Greene 345 kV OH Madison Active AEP 577 577 397.3 Capacity Generation Interconnection Solar; Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2148_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2148_imp.pdf Document Posted In Progress N/A N/A 2/20/2019 N/A N/A 6/1/2022 N/A N No
AE2-282 + East Fayette 138 kV OH Fulton Active ATSI 67 67 43.9 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2282_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2282_imp.pdf Document Posted In Progress https://www.pjm.com/pub/planning/project-queues/isa/ae2_282_isa2.pdf Interim Study N/A N/A N/A 3/29/2019 N/A N/A 9/15/2021 N/A N No
AE2-282 - East Fayette 138 kV OH Fulton Active ATSI 67 67 43.9 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2282_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2282_imp.pdf Document Posted In Progress N/A N/A 3/29/2019 N/A N/A 9/15/2021 N/A N No
AE2-285 + Maysville 69 kV MC Solar I PA Mercer Engineering and Procurement ATSI 50 50 30 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2285_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2285_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae2285_fac.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/isa/ae2_285_isa.pdf Document Posted N/A https://www.pjm.com/pub/planning/project-queues/csa/ae2_285_csa.pdf Document Posted N/A N/A 3/29/2019 N/A N/A 1/2/2023 1/2/2023 N/A N No
AE2-285 - Maysville 69 kV PA Mercer Active ATSI 50 50 30 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2285_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2285_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/ae2285_fac.pdf Document Posted N/A N/A 3/29/2019 N/A N/A 6/30/2022 N/A N No
AE2-334 + Clayton-Williamstown 69 kV NJ Gloucester Active AEC 44 44 26.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2334_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2334_imp.pdf Document Posted In Progress N/A N/A 3/31/2019 N/A N/A 6/30/2022 N/A N No
AE2-334 - Clayton-Williamstown 69 kV NJ Gloucester Active AEC 44 44 28.7 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2334_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2334_imp.pdf Document Posted In Progress N/A N/A 3/31/2019 N/A N/A 6/30/2022 N/A N No
AF1-003 + Hawkins Gate-Billingsley Rd 69 kV MD Charles Active SMECO 20 20 9.5 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af1003_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1003_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/af1003_fac.pdf Document Posted Not Required N/A N/A 4/1/2019 N/A N/A 7/30/2021 N/A N No
AF1-003 - Hawkins Gate-Billingsley Rd 69 kV MD Charles Active SMECO 20 20 9.5 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af1003_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1003_imp.pdf Document Posted In Progress N/A N/A 4/1/2019 N/A N/A 7/30/2021 N/A N No
AF1-005 + Charles County Solar I MD Charles Active SMECO 20 20 9.9 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af1005_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1005_imp.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/facilities/af1005_fac.pdf Document Posted Not Required N/A N/A 4/1/2019 N/A N/A 7/30/2021 N/A N No
AF1-005 - Charles County Solar I MD Charles Active SMECO 20 20 9.9 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af1005_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1005_imp.pdf Document Posted In Progress N/A N/A 4/1/2019 N/A N/A 7/30/2021 N/A N No
AF1-014 + Harmony Village-Shackleford 115 kV Walnut Solar I VA King and Queen Engineering and Procurement Dominion 149.9 19.9 7.2 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af1014_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1014_imp.pdf Document Posted Not Required https://www.pjm.com/pub/planning/project-queues/isa/af1_014_isa.pdf Document Posted N/A Not Required N/A N/A 4/3/2019 N/A N/A 12/31/2023 12/31/2023 N/A N No
AF1-014 - Harmony Village-Shackleford 115 kV VA King and Queen Active Dominion 149.9 19.9 7.2 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af1014_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1014_imp.pdf Document Posted In Progress N/A N/A 4/3/2019 N/A N/A 10/1/2019 N/A N No
AF1-101 + Oyster Creek 230 kV III NJ Ocean Withdrawn JCPL 800 800 224.8 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/af1101_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1101_imp.pdf Document Posted Withdrawn N/A N/A 9/6/2019 N/A N/A 7/15/2021 11/23/2022 N/A N No
AF1-101 - Oyster Creek 230 kV III NJ Atlantic Active JCPL 800 800 224.8 Capacity Generation Interconnection Offshore Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/af1101_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af1101_imp.pdf Document Posted In Progress N/A N/A 9/6/2019 N/A N/A 11/23/2022 N/A N No
AF2-076 + Suffolk-Nucor Steel 230 kV VA City of Suffolk Withdrawn Dominion 50 50 30 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2076_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2076_imp.pdf Document Posted Withdrawn N/A N/A 1/31/2020 N/A N/A 7/23/2021 12/1/2023 N/A N No
AF2-076 - Suffolk-Nucor Steel 230 kV VA City of Suffolk Active Dominion 50 50 30 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2076_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2076_imp.pdf Document Posted In Progress N/A N/A 1/31/2020 N/A N/A 12/1/2023 N/A N No
AF2-314 + Vandergrift-Guffy Junction 25 kV PA Armstrong Active APS 10 10 6 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2314_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2314_imp.pdf Document Posted Not Required Not Required N/A N/A 3/30/2020 N/A N/A 9/1/2022 N/A N No
AF2-314 - Vandergrift-Guffy Junction 25 kV PA Armstrong Active APS 10 10 6 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2314_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2314_imp.pdf Document Posted In Progress N/A N/A 3/30/2020 N/A N/A 9/1/2022 N/A N No
AF2-341 + Maysville138 kV PA Mercer Withdrawn ATSI 20 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2341_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2341_imp.pdf Document Posted Withdrawn N/A N/A 3/31/2020 N/A N/A 7/23/2021 12/31/2023 N/A N No
AF2-341 - Maysville138 kV PA Mercer Active ATSI 20 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2341_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2341_imp.pdf Document Posted In Progress N/A N/A 3/31/2020 N/A N/A 12/31/2023 N/A N No
AF2-342 + Maysville138 kV II PA Mercer Withdrawn ATSI 40 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2342_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2342_imp.pdf Document Posted Withdrawn N/A N/A 3/31/2020 N/A N/A 7/23/2021 12/31/2023 N/A N No
AF2-342 - Maysville138 kV II PA Mercer Active ATSI 40 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2342_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2342_imp.pdf Document Posted In Progress N/A N/A 3/31/2020 N/A N/A 12/31/2023 N/A N No
AF2-343 + Maysville 138 kV III PA Mercer Active ATSI 60 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2343_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2343_imp.pdf Document Posted Withdrawn N/A N/A 3/31/2020 N/A N/A 7/23/2021 12/31/2023 N/A N No
AF2-343 - Maysville 138 kV III PA Mercer Active ATSI 60 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2343_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2343_imp.pdf Document Posted In Progress N/A N/A 3/31/2020 N/A N/A 12/31/2023 N/A N No
AF2-344 + Maysville 138 kV IV PA Mercer Withdrawn ATSI 80 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2344_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2344_imp.pdf Document Posted Withdrawn N/A N/A 3/31/2020 N/A N/A 7/23/2021 12/31/2023 N/A N No
AF2-344 - Maysville 138 kV IV PA Mercer Active ATSI 80 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2344_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2344_imp.pdf Document Posted In Progress N/A N/A 3/31/2020 N/A N/A 12/31/2023 N/A N No
AF2-345 + Maysville 138 kV V PA Mercer Withdrawn ATSI 100 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2345_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2345_imp.pdf Document Posted Withdrawn N/A N/A 3/31/2020 N/A N/A 7/23/2021 12/31/2023 N/A N No
AF2-345 - Maysville 138 kV V PA Mercer Active ATSI 100 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/af2345_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/af2345_imp.pdf Document Posted In Progress N/A N/A 3/31/2020 N/A N/A 12/31/2023 N/A N No
AG1-008 + Tunis-Mapleton 115 kV NC Hertford Active Dominion 150 150 100 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1008_fea.pdf Document Posted In Progress N/A N/A 5/1/2020 N/A N/A 12/15/2024 N/A N No
AG1-008 - Tunis-Mapleton 115 kV NC Hertford Active Dominion 150 150 100 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1008_fea.pdf Document Posted N/A N/A 5/1/2020 N/A N/A 12/15/2024 N/A N No
AG1-050 + Milton 69 kV PA Northumberland Active PPL 90 20 20 Capacity Generation Interconnection Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1050_fea.pdf Document Posted In Progress N/A N/A 7/17/2020 N/A N/A 6/30/2022 N/A N No
AG1-050 - Milton 69 kV PA Northumberland Active PPL 90 20 20 Capacity Generation Interconnection Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1050_fea.pdf Document Posted N/A N/A 7/17/2020 N/A N/A 6/30/2022 N/A N No
AG1-060 + Eldred 69 kV PA Schuylkill Active PPL 174.8 174.8 25.7 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1060_fea.pdf Document Posted In Progress N/A N/A 7/29/2020 N/A N/A 5/31/2022 N/A N No
AG1-060 - Eldred 69 kV PA Schuylkill Active PPL 174.8 174.8 25.7 Capacity Generation Interconnection Wind https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1060_fea.pdf Document Posted N/A N/A 7/29/2020 N/A N/A 5/31/2022 N/A N No
AG1-075 + Purdy-Sapony 115 kV VA Greensville Active Dominion 150 150 93.2 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1075_fea.pdf Document Posted In Progress N/A N/A 7/31/2020 N/A N/A 10/15/2024 N/A N No
AG1-075 - Purdy-Sapony 115 kV VA Greensville Active Dominion 150 150 93.2 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1075_fea.pdf Document Posted N/A N/A 7/31/2020 N/A N/A 10/15/2024 N/A N No
AG1-106 + Thelma 230 kV NC Northhampton Active Dominion 350 50 34.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1106_fea.pdf Document Posted In Progress N/A N/A 8/28/2020 N/A N/A 6/1/2024 N/A N No
AG1-106 - Thelma 230 kV NC Northhampton Active Dominion 350 50 34.4 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1106_fea.pdf Document Posted N/A N/A 8/28/2020 N/A N/A 6/1/2024 N/A N No
AG1-148 + McCarter 26.4 kV Rutgers Generation NJ Essex Engineering and Procurement PSEG 5 5 0 Energy Generation Interconnection Natural Gas https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1148_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1148_imp.pdf Document Posted Not Required N/A Wholesale Market Participation Agreement https://www.pjm.com/pub/planning/project-queues/wmpa/ag1148_wmpa.pdf https://www.pjm.com/pub/planning/project-queues/csa/ag1148_wmpa.pdf Not Required N/A N/A 9/9/2020 N/A N/A 10/3/2022 10/3/2022 N/A N No
AG1-148 - McCarter 26.4 kV NJ Essex Active PSEG 5 5 0 Energy Generation Interconnection Natural Gas https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1148_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1148_imp.pdf Document Posted Not Required Not Required N/A N/A 9/9/2020 N/A N/A 11/9/2021 N/A N No
AG1-157 + Macungie-Emmaus Tie 69 kV PA Lehigh Active PPL 7.4 7.37 0 Energy Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1157_fea.pdf Document Posted In Progress N/A N/A 9/11/2020 N/A N/A 6/16/2022 N/A N No
AG1-157 - Macungie-Emmaus Tie 69 kV PA Lehigh Active PPL 7.4 7.37 0 Energy Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1157_fea.pdf Document Posted N/A N/A 9/11/2020 N/A N/A 6/16/2022 N/A N No
AG1-315 + Lardin-Grays Landing 12.47 kV PA Fayette Active APS 2 2 0.84 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1315_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1315_imp.pdf Document Posted Not Required Not Required N/A N/A 9/29/2020 N/A N/A 12/31/2021 N/A N No
AG1-315 - Lardin-Grays Landing 12.47 kV PA Fayette Active APS 2 2 0.84 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1315_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1315_imp.pdf Document Posted In Progress N/A N/A 9/29/2020 N/A N/A 12/31/2021 N/A N No
AG1-327 + Ringgold – East Waynesboro 138 kV PA Franklin Active APS 35 35 23.1 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1327_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 12/31/2023 N/A N No
AG1-327 - West Waynesboro-East Waynesboro 138 kV PA Franklin Active APS 35 35 23.1 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1327_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 12/31/2023 N/A N No
AG1-392 + Gold 115 kV I PA Potter Active PENELEC 40 40 24 Capacity Generation Interconnection Solar; Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1392_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392 - Gold 115 kV IV PA Potter Active PENELEC 40 40 24 Capacity Generation Interconnection Solar; Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1392_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392A + Gold 115 kV II PA Potter Active PENELEC 40 40 24 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1391_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392A - Gold 115 kV III PA Potter Active PENELEC 40 40 24 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1391_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392B + Gold 115 kV III PA Potter Active PENELEC 20 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1390_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392B - Gold 115 kV II PA Potter Active PENELEC 20 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1390_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392C + Gold 115 kV IV PA Potter Active PENELEC 20 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1389_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-392C - Gold 115 kV I PA Potter Active PENELEC 20 20 12 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1389_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 6/1/2022 N/A N No
AG1-455 + Springboro-Venango Junction 115 kV PA Crawford Active PENELEC 112.5 35 35 Capacity Generation Interconnection Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1455_fea.pdf Document Posted In Progress N/A N/A 9/30/2020 N/A N/A 12/31/2022 N/A N No
AG1-455 - Springboro-Venango Junction 115 kV PA Crawford Active PENELEC 112.5 35 35 Capacity Generation Interconnection Storage https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1455_fea.pdf Document Posted N/A N/A 9/30/2020 N/A N/A 12/31/2022 N/A N No
AG1-498 + Mount Bethel 12.47 kV Martins Creek Solar PA Northampton Engineering and Procurement PPL 8.8 8.8 3.7 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1498_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1498_imp.pdf Document Posted Not Required N/A Wholesale Market Participation Agreement https://www.pjm.com/pub/planning/project-queues/wmpa/ag1498_wmpa.pdf https://www.pjm.com/pub/planning/project-queues/csa/ag1498_wmpa.pdf Not Required N/A N/A 9/30/2020 N/A N/A 4/1/2024 4/1/2024 N/A N No
AG1-498 - Mount Bethel 12.47 kV PA Northampton Active PPL 8.8 8.8 3.7 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1498_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1498_imp.pdf Document Posted Not Required Not Required N/A N/A 9/30/2020 N/A N/A 5/31/2022 N/A N No
AG1-563 + Bennett-Farmingdale 2 34.5 kV AG1-563 NJ Monmouth In Service JCPL 2 0 0.7 0 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1563_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1563_imp.pdf Document Posted Not Required https://www.pjm.com/pub/planning/project-queues/isa/ag1_563_isa.pdf Document Posted N/A Not Required N/A N/A 9/30/2020 N/A N/A 6/1/2020 7/16/2021 N/A N No
AG1-563 - Bennett-Farmingdale 2 34.5 kV NJ Monmouth Active JCPL 2 0 0.7 Capacity Generation Interconnection Solar https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1563_fea.pdf Document Posted https://www.pjm.com/pub/planning/project-queues/impact_studies/ag1563_imp.pdf Document Posted Not Required N/A N/A 9/30/2020 N/A N/A 6/1/2020 N/A N No
AG2-347 + Indian River 230 kV DE Sussex Active DPL 448.8 448.8 121.2 Capacity Generation Interconnection Wind In Progress N/A N/A 3/26/2021 N/A N/A 8/31/2025 N/A N No
AG2-347 - Indian River 230 kV DE Sussex Active DPL 448.8 448.8 121.2 Capacity Generation Interconnection Offshore Wind In Progress N/A N/A 3/26/2021 N/A N/A 8/31/2025 N/A N No
AG2-397 + West Boyertown 13.2 kV PA Columbia Active ME 3 3 0 Energy Generation Interconnection In Progress N/A N/A 3/30/2021 N/A N/A 6/21/2022 N/A Y No
AG2-397 - TBD 12 kV PA Columbia Active ME Energy Generation Interconnection In Progress N/A N/A 3/30/2021 N/A N/A 6/21/2022 N/A Y No
AG2-429 + Burma - Armstrong 138 kV PA Clarion Active APS 69 69 53.86 Capacity Generation Interconnection Solar In Progress N/A N/A 3/30/2021 N/A N/A 2/29/2024 N/A N No
AG2-429 - Burma - Armstrong 138 kV PA Clarion Active APS 69 69 55.2 Capacity Generation Interconnection Solar; Storage In Progress N/A N/A 3/30/2021 N/A N/A 2/29/2024 N/A N No
AG2-439 + Oxbow 34.5 kV PA Wyoming Active PENELEC 9.8 9.8 5.3 Capacity Generation Interconnection Solar In Progress N/A N/A 3/30/2021 N/A N/A 5/25/2021 6/15/2023 N/A N No
AG2-439 - Lenox 34 kV II PA Wyoming Active PENELEC 9.8 9.8 5.3 Capacity Generation Interconnection Solar In Progress N/A N/A 3/30/2021 N/A N/A 5/25/2021 6/15/2023 N/A N No
AG2-479 + Penns Tap-Richfield Tie 69 kV II PA Snyder Active PPL 20 0 4.1 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 10/31/2022 N/A N No
AG2-479 - Penns Tap-Richfield Tie 69 kV II PA Snyder Active PPL 20 0 5 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 10/31/2022 N/A N No
AG2-480 + Derry Tap-Derry Bus 69 kV II PA Montour Active PPL 20 0 4.1 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 5/31/2022 N/A N No
AG2-480 - Derry Tap-Derry Bus 69 kV II PA Montour Active PPL 20 0 5 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 5/31/2022 N/A N No
AG2-481 + Derry Tap-Derry Bus 69 kV III PA Northumberland Active PPL 20 0 4.1 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 7/31/2022 N/A N No
AG2-481 - Derry Tap-Derry Bus 69 kV III PA Northumberland Active PPL 20 0 5 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 7/31/2022 N/A N No
AG2-482 + Bowman’s Mill-Scott 69 kV II PA Columbia Active PPL 35 0 8 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 11/15/2022 N/A N No
AG2-482 - Bowman’s Mill-Scott 69 kV II PA Columbia Active PPL 35 0 8.7 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 11/15/2022 N/A N No
AG2-484 + Mifflintown Bus-Mifflintown Tap 69 kV II PA Juniata Active PPL 20 0 4.6 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 8/31/2022 N/A N No
AG2-484 - Mifflintown Bus-Mifflintown Tap 69 kV II PA Juniata Active PPL 20 0 5 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 8/31/2022 N/A N No
AG2-486 + Bloomsburg-Columbia 69 kV II PA Columbia Active PPL 20 0 4.1 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/15/2022 N/A N No
AG2-486 - Bloomsburg-Columbia 69 kV II PA Columbia Active PPL 20 0 5 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/15/2022 N/A N No
AG2-493 + Phillipsburg Bus II 34.5 kV VA Prince Edward Active PENELEC 5 5 0 Energy Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 6/21/2022 N/A Y No
AG2-493 - Winburne 34.5 kV VA Prince Edward Active PENELEC 5 5 0 Energy Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 6/21/2022 N/A Y No
AG2-494 + Keewaydin 34.5 kV OH Madison Withdrawn PENELEC Energy Generation Interconnection Withdrawn N/A N/A 3/31/2021 N/A N/A 7/23/2021 6/21/2022 N/A Y No
AG2-494 - Keewaydin 34.5 kV PA Clarion Active PENELEC 5 5 0 Energy Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 6/21/2022 N/A Y No
AG2-495 + Phillipsburg Bus I 34.5 kV PA Bedford Active PENELEC Energy Generation Interconnection In Progress N/A N/A 3/31/2021 N/A N/A 6/21/2022 N/A Y No
AG2-495 - Allport 34.5 kV PA Bedford Active PENELEC Energy Generation Interconnection In Progress N/A N/A 3/31/2021 N/A N/A 6/21/2022 N/A Y No
AG2-496 + Bloom 34.5 kV OH Madison Withdrawn PENELEC Energy Generation Interconnection Withdrawn N/A N/A 3/31/2021 N/A N/A 7/23/2021 6/21/2022 N/A Y No
AG2-496 - Bloom 34.5 kV PA Beaver Active PENELEC 5 5 0 Energy Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 6/21/2022 N/A Y No
AG2-525 + Bonney Forge 23 kV II MI Cass Withdrawn PENELEC Energy Generation Interconnection Withdrawn N/A N/A 3/31/2021 N/A N/A 7/13/2021 6/1/2023 N/A Y No
AG2-525 - Bonney Forge 23 kV II PA Huntingdon Active PENELEC 5 5 0 Energy Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 6/1/2023 N/A Y No
AG2-550 + Bluff Point - Randolph 138 kV IN Randolph Active AEP 200 100 60 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 10/31/2024 N/A N No
AG2-550 - Bluff Point - Randolph 138 kV IN Randolph Active AEP 100 100 60 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 10/31/2024 N/A N No
AG2-551 + Bluff Point - Randolph 138 kV IN Randolph Active AEP 250 50 20 Capacity Generation Interconnection Storage In Progress N/A N/A 3/31/2021 N/A N/A 10/31/2024 N/A N No
AG2-551 - Bluff Point - Randolph 138 kV IN Randolph Active AEP 50 50 20 Capacity Generation Interconnection Storage In Progress N/A N/A 3/31/2021 N/A N/A 10/31/2024 N/A N No
AG2-572 + Scottsville - Bremo 138 kV VA Buckingham Active AEP 50 50 30 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 3/25/2024 N/A N No
AG2-572 - Scottsville - Bremo 138 kV VA Buckingham Active AEP 80 80 48 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 3/25/2024 N/A N No
AG2-576 + Varner 345 kV IN DeKalb Active AEP 180 180 108 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2024 N/A N No
AG2-576 - Varner 345 kV IN Jay Active AEP 180 180 108 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2024 N/A N No
AG2-578 + Jay 69 kV IN Jay Active AEP 50 50 30 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2024 N/A N No
AG2-578 - Armstrong 69 kV IN Jay Active AEP 50 50 30 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2024 N/A N No
AG2-615 + Carlos Junction 138 kV MD Allegany Active APS 100 100 62.6 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2023 N/A N No
AG2-615 - Carlos Junction 138 kV MD Allegany Active APS 100 100 64.8 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2023 N/A N No
AG2-618 + Morgantown 230 kV MD Charles Active PEPCO 110 110 69.1 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2023 N/A N No
AG2-618 - Morgantown 230 kV MD Charles Active PEPCO 110 110 71.5 Capacity Generation Interconnection Solar In Progress N/A N/A 3/31/2021 N/A N/A 12/31/2023 N/A N No
AH1-003 + Tazewell - AB1-122 345 kV IL Woodford Active ComEd 130 130 19.11 Capacity Generation Interconnection Wind In Progress N/A N/A 4/1/2021 N/A N/A 12/31/2024 N/A N No
AH1-005 + East Towanda-South Troy 115 kV II PA Bradford Active PENELEC 54 23 14.8 Capacity Generation Interconnection Solar In Progress N/A N/A 4/9/2021 N/A N/A 9/30/2025 N/A N No
AH1-005 - East Towanda-South Troy 115 kV II PA Bradford Active PENELEC 54 23 15.7 Capacity Generation Interconnection Solar In Progress N/A N/A 4/9/2021 N/A N/A 9/30/2025 N/A N No
AH1-010 + Stony River - Buffalo Coal 66 kV WV Grant Active APS 20 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 4/19/2021 N/A N/A 12/31/2023 N/A N No
AH1-010 - Stony River - Buffalo Coal 69 kV WV Grant Active APS 20 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 4/19/2021 N/A N/A 12/31/2023 N/A N No
AH1-011 + Fulton - Tidd 69 kV WV Brooke Active AEP 20 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 4/19/2021 N/A N/A 12/31/2023 N/A N No
AH1-011 - Fulton - Tidd 69 kV WV Brooke Active APS 20 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 4/19/2021 N/A N/A 12/31/2023 N/A N No
AH1-016 + Central Hardin 138 kV KY Hardin Active EKPC 280 280 168 Capacity Generation Interconnection Solar In Progress N/A N/A 4/22/2021 N/A N/A 12/2/2024 N/A N No
AH1-016 - Hardin Co - Daviess Co 345 kV KY Hardin Active EKPC 280 280 168 Capacity Generation Interconnection Solar In Progress N/A N/A 4/22/2021 N/A N/A 12/2/2024 N/A N No
AH1-022 + Allen 13.2 kV PA Cumberland Active ME 3 3 2 Capacity Generation Interconnection Solar In Progress N/A N/A 5/12/2021 N/A N/A 11/30/2022 N/A N No
AH1-022 - Cumberland 12 kV PA Cumberland Active ME 3 3 2 Capacity Generation Interconnection Solar In Progress N/A N/A 5/12/2021 N/A N/A 11/30/2022 N/A N No
AH1-033 + Sligo 34.5 kV NC Currituck Active Dominion 19.5 19.5 13 Capacity Generation Interconnection Solar In Progress N/A N/A 6/14/2021 N/A N/A 8/15/2024 N/A N No
AH1-033 - Sligo Solar NC Currituck Active Dominion 19.5 19.5 13 Capacity Generation Interconnection Solar In Progress N/A N/A 6/14/2021 N/A N/A 8/15/2024 N/A N No
AH1-035 + Plymouth 34.5 kV NC Washington Active Dominion 20 20 13.5 Capacity Generation Interconnection Solar In Progress N/A N/A 6/14/2021 N/A N/A 9/15/2024 N/A N No
AH1-039 + Mt. Hermon 23 kV MD Wicomico Active DPL 20 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 6/18/2021 N/A N/A 10/1/2023 N/A N No
AH1-040 + Mackeys - Creswell 115 kV NC Washington Active Dominion 150 150 90 Capacity Generation Interconnection Solar In Progress N/A N/A 6/23/2021 N/A N/A 7/1/2025 N/A N No
AH1-041 + Pennville 138 kV IN Jay Active AEP 125 125 75 Capacity Generation Interconnection Solar In Progress N/A N/A 6/23/2021 N/A N/A 7/1/2025 N/A N No
AH1-044 + Nelson - Electric Junction 345 kV IL Lee Active ComEd 200 200 120 Capacity Generation Interconnection Solar In Progress N/A N/A 6/30/2021 N/A N/A 12/31/2024 N/A N No
AH1-046 + Peach Bottom 500 kV PA York Active PECO 25 25 15 Capacity Generation Interconnection Solar In Progress N/A N/A 7/1/2021 N/A N/A 6/1/2023 N/A N No
AH1-049 + Page 34.5 kV PA Erie Active PENELEC 20 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 7/7/2021 N/A N/A 7/1/2023 N/A N No
AH1-050 + Eclipse-Piney 115 kV PA Venango Active PENELEC 50 50 30 Capacity Generation Interconnection Solar In Progress N/A N/A 7/7/2021 N/A N/A 7/1/2023 N/A N No
AH1-051 + Eclipse-Piney 115 kV II PA Venango Active PENELEC 80 30 18 Capacity Generation Interconnection Solar In Progress N/A N/A 7/7/2021 N/A N/A 7/1/2023 N/A N No
AH1-052 + Boydton Plank Road 115 kV VA Mecklenburg Active Dominion 260 60 36 Capacity Generation Interconnection Solar In Progress N/A N/A 7/7/2021 N/A N/A 4/1/2025 N/A N No
AH1-054 + Whitings 34.5 kV NJ Ocean Active JCPL 8.3 8.25 3.465 Capacity Generation Interconnection Solar In Progress N/A N/A 7/9/2021 N/A N/A 7/8/2022 N/A N No
AH1-058 + Galion 138 kV OH Morrow Active ATSI 204 40 24 Capacity Generation Interconnection Solar In Progress N/A N/A 7/16/2021 N/A N/A 12/31/2024 N/A N No
AH1-060 + Cardington-Liberty 69 kV OH Morrow Active ATSI 101 20 12 Capacity Generation Interconnection Solar In Progress N/A N/A 7/20/2021 N/A N/A 12/31/2024 N/A N No