Changes in PJM Queue between June 30th, 2021 and July 6th, 2021.
Where an existing project has some updated field, you’ll find two rows for that project, with the new entry on top, updated fields highlighted in green, and deprecated fields highlighted in red in the bottom row.
Fully new queue positions appear as individual rows with all fields highlighted green.
create_output_table(ctable_queues)
## Creating HTML table for first ${limit_html} rows
| QueueNumber | chng_type | Name | CommercialName | State | County | Status | TransmissionOwner | MaximumFacilityOutput | MWEnergy | MWCapacity | MWInService | CapacityorEnergy | ProjectType | Fuel | ProjectACOrDC | RightsMW | InitialStudy | FeasibilityStudy | FeasibilityStudyStatus | SystemImpactStudy | SystemImpactStudyStatus | FacilitiesStudy | FacilitiesStudyStatus | InterimInterconnectionServiceAgreement | InterimInterconnectionServiceAgreementStatus | WholesaleMarketParticipationAgreement | ConstructionServiceAgreement | ConstructionServiceAgreementStatus | UpgradeConstructionServiceAgreement | UpgradeConstructionServiceAgreementStatus | BackfeedDate | QueueDate | LongTermFirmServiceStartDate | LongTermFirmServiceEndDate | TestEnergyDate | WithdrawalDate | WithdrawnRemarks | ProjectedInServiceDate | RevisedInServiceDate | ActualInServiceDate | SuspensionDate | AttachmentType | AlternateQueue | SlideQueue |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| AB1-005 | + | Harrisonville 13kV | MD | Baltimore County | Withdrawn | BGE | 1.3 | 1.3 | 0 | Energy | Generation Interconnection | Natural Gas | Not Required | Not Required | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab1005_wmpa.pdf | Not Required | N/A | N/A | 5/18/2015 | N/A | N/A | 10/1/2020 | 7/2/2021 | 12/1/2021 | 12/1/2021 | N/A | Y | No | |||||||||||||
| AB1-005 | - | Harrisonville 13kV | MD | Baltimore County | Under Construction | BGE | 1.3 | 1.3 | 0 | Energy | Generation Interconnection | Natural Gas | Not Required | Not Required | Not Required | N/A | Wholesale Market Participation Agreement | https://www.pjm.com/pub/planning/project-queues/wmpa/ab1005_wmpa.pdf | Not Required | N/A | N/A | 5/18/2015 | N/A | N/A | 10/1/2020 | 12/1/2021 | 12/1/2021 | N/A | Y | No | ||||||||||||||
| AB2-158 | + | Louisa-South Anna 230kV | Belcher Solar | VA | Louisa | In Service | Dominion | 88.2 | 88.2 | 61 | 88.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2158_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2158_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2158_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_158_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_158_csa.pdf | Document Posted | N/A | N/A | 4/29/2016 | N/A | N/A | 5/31/2021 | 12/1/2020 | 12/1/2020 | 6/30/2021 | N/A | N | No | |||||||
| AB2-158 | - | Louisa-South Anna 230kV | Belcher Solar | VA | Louisa | Partially in Service - Under Construction | Dominion | 88.2 | 88.2 | 61 | 88.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ab2158_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ab2158_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ab2158_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ab2_158_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ab2_158_csa.pdf | Document Posted | N/A | N/A | 4/29/2016 | N/A | N/A | 5/31/2021 | 12/1/2020 | 12/1/2020 | 5/24/2021 | N/A | N | No | |||||||
| AC1-074 | + | Jacksonville-Renaker 138kV I | Bluebird Solar | KY | Harrison | Engineering and Procurement | EKPC | 80 | 80 | 56 | 1 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1074_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1074_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1074_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_074_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_074_csa.pdf | Document Posted | N/A | N/A | 9/29/2016 | N/A | N/A | 6/1/2023 | 6/1/2023 | N/A | N | No | |||||||||
| AC1-074 | - | Jacksonville-Renaker 138kV I | Bluebird Solar | KY | Harrison | Engineering and Procurement | EKPC | 80 | 80 | 56 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1074_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1074_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1074_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_074_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_074_csa.pdf | Document Posted | N/A | N/A | 9/29/2016 | N/A | N/A | 11/30/2022 | 11/30/2022 | N/A | N | No | ||||||||||
| AC1-075 | + | Perth-Hickory Grove 115kV | Stagecoach Solar | VA | Halifax | In Service | Dominion | 60 | 60 | 38.3 | 60 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1075_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1075_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1075_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_075_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_075_csa.pdf | Document Posted | N/A | N/A | 3/3/2021 | 9/29/2016 | N/A | N/A | 3/30/2021 | 12/31/2021 | 12/31/2021 | 4/1/2021 | N/A | N | No | ||||||
| AC1-075 | - | Perth-Hickory Grove 115kV | Stagecoach Solar | VA | Halifax | Partially in Service - Under Construction | Dominion | 60 | 60 | 38.3 | 33 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1075_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1075_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1075_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_075_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_075_csa.pdf | Document Posted | N/A | N/A | 3/3/2021 | 9/29/2016 | N/A | N/A | 3/30/2021 | 12/31/2021 | 12/31/2021 | N/A | N | No | |||||||
| AC1-080 | + | Perth-Hickory Grove 115kV | Stagecoach Solar | VA | Halifax | In Service | Dominion | 20 | 20 | 12.8 | 20 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1080_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1080_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1080_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_080_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_080_csa.pdf | Document Posted | N/A | N/A | 3/3/2021 | 9/30/2016 | N/A | N/A | 3/30/2021 | 12/31/2021 | 12/31/2021 | N/A | N | No | |||||||
| AC1-080 | - | Perth-Hickory Grove 115kV | Stagecoach Solar | VA | Halifax | Under Construction | Dominion | 20 | 20 | 12.8 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac1080_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac1080_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac1080_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac1_080_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ac1_080_csa.pdf | Document Posted | N/A | N/A | 3/3/2021 | 9/30/2016 | N/A | N/A | 3/30/2021 | 12/31/2021 | 12/31/2021 | N/A | N | No | ||||||||
| AC2-075 | + | Jacksonville-Renaker 138 kV | Bluebird Solar | KY | Harrison | Engineering and Procurement | EKPC | 100 | 20 | 13.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2075_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2075_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2075_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ac2_075_isa.pdf | Document Posted | N/A | N/A | N/A | 2/27/2017 | N/A | N/A | 6/1/2023 | 6/1/2023 | N/A | N | No | ||||||||||||
| AC2-075 | - | Jacksonville-Renaker 138 kV | KY | Harrison | Active | EKPC | 20 | 20 | 13.3 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ac2075_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ac2075_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ac2075_fac.pdf | Document Posted | N/A | N/A | 2/27/2017 | N/A | N/A | 6/1/2019 | N/A | N | No | |||||||||||||||||
| AD1-119 | + | Payne 69 kV | Timber Road Solar Park | OH | Paulding | Engineering and Procurement | AEP | 49.9 | 49.9 | 18.96 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1119_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1119_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1119_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad1_119_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad1_119_csa.pdf | Document Posted | N/A | N/A | 9/28/2017 | N/A | N/A | 10/1/2022 | 10/1/2022 | N/A | N | No | ||||||||||
| AD1-119 | - | Payne 69 kV | OH | Paulding | Active | AEP | 49.9 | 49.9 | 18.96 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad1119_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad1119_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad1119_fac.pdf | Document Posted | N/A | N/A | 9/28/2017 | N/A | N/A | 10/31/2020 | N/A | N | No | |||||||||||||||||
| AD2-076 | + | Carville 138 kV | Concho Solar I | MD | Queen Anne’s | Engineering and Procurement | DPL | 49 | 49 | 18.62 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2076_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2076_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2076_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_076_isa.pdf | Document Posted | N/A | https://www.pjm.com/pub/planning/project-queues/csa/ad2_076_csa.pdf | Document Posted | N/A | N/A | 3/15/2018 | N/A | N/A | 6/3/2024 | 6/3/2024 | N/A | N | No | ||||||||||
| AD2-076 | - | Carville 138 kV | Concho Solar I | MD | Queen Anne’s | Engineering and Procurement | DPL | 49 | 49 | 18.62 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ad2076_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ad2076_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ad2076_fac.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/isa/ad2_076_isa.pdf | Document Posted | N/A | N/A | N/A | 3/15/2018 | N/A | N/A | 6/3/2024 | 6/3/2024 | N/A | N | No | ||||||||||||
| AE1-095 4966859 | + | PJM-HUDSON | N/A | N/A | Withdrawn | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966859_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2020 | 6/1/2021 | 2/27/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-095 4966859 | - | PJM-HUDSON | N/A | N/A | Withdrawn | Hudson Transmission Partners, LLC | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966859_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2020 | 6/1/2021 | 2/27/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-096 4966862 | + | PJM-HUDSON | N/A | N/A | Withdrawn | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966862_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2021 | 6/1/2022 | 2/27/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-096 4966862 | - | PJM-HUDSON | N/A | N/A | Withdrawn | Hudson Transmission Partners, LLC | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966862_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2021 | 6/1/2022 | 2/27/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-097 4966877 | + | PJM-HUDSON | N/A | N/A | Withdrawn | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966877_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2022 | 6/1/2027 | 2/27/2019 | N/A | PP | No | |||||||||||||||||||||||||
| AE1-097 4966877 | - | PJM-HUDSON | N/A | N/A | Withdrawn | Hudson Transmission Partners, LLC | 62 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966877_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/30/2018 | 6/1/2022 | 6/1/2027 | 2/27/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-110 4966477 | + | PJM-DUK | N/A | N/A | Withdrawn | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966477_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966477_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2030 | 2/28/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-110 4966477 | - | PJM-DUK | N/A | N/A | Withdrawn | Morgan Stanley Capital Group Inc. | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966477_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966477_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2030 | 2/28/2019 | N/A | PP | No | |||||||||||||||||||||||
| AE1-111 4966479 | + | PJM-DUK | N/A | N/A | Withdrawn | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966479_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966479_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2031 | 2/28/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-111 4966479 | - | PJM-DUK | N/A | N/A | Withdrawn | Morgan Stanley Capital Group Inc. | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966479_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966479_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2031 | 2/28/2019 | N/A | PP | No | |||||||||||||||||||||||
| AE1-112 4966484 | + | PJM-DUK | N/A | N/A | Withdrawn | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966484_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966484_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2032 | 2/28/2019 | N/A | PP | No | ||||||||||||||||||||||||
| AE1-112 4966484 | - | PJM-DUK | N/A | N/A | Withdrawn | Morgan Stanley Capital Group Inc. | 100 | Energy | Long-Term Firm Transmission | https://www.pjm.com/pub/planning/project-queues/ft-is/4966484_ltf1.pdf | https://www.pjm.com/pub/planning/project-queues/ft-feas/4966484_ltf1.pdf | Executed Agreement and/or Study | N/A | N/A | 8/28/2018 | 1/1/2025 | 1/1/2032 | 2/28/2019 | N/A | PP | No | |||||||||||||||||||||||
| AE2-035 | + | Lena 138 kV | IL | Stephenson | Active | ComEd | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2035_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2035_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/ae2035_fac.pdf | Document Posted | N/A | N/A | 1/15/2019 | N/A | N/A | 5/21/2021 | N/A | N | No | |||||||||||||||||
| AE2-035 | - | Lena 138 kV | IL | Stephenson | Active | ComEd | 50 | 50 | 21 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ae2035_fea.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/impact_studies/ae2035_imp.pdf | Document Posted | https://www.pjm.com/pub/planning/project-queues/facilities/Combined with AD2-172 | Document Posted | N/A | N/A | 1/15/2019 | N/A | N/A | 5/21/2021 | N/A | N | No | |||||||||||||||||
| AG1-008 | + | Tunis-Mapleton 115 kV | NC | Hertford | Active | Dominion | 150 | 150 | 100 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1008_fea.pdf | Document Posted | N/A | N/A | 5/1/2020 | N/A | N/A | 12/15/2024 | N/A | N | No | |||||||||||||||||||||
| AG1-008 | - | Tunis-Mapleton 115 kV | NC | Hertford | Withdrawn | Dominion | 150 | 150 | 100 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1008_fea.pdf | Document Posted | N/A | N/A | 5/1/2020 | N/A | N/A | 4/13/2021 | 12/15/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-048 | + | Jetersville-Ponton 115 kV | VA | Amelia | Active | Dominion | 106.3 | 106.25 | 52.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1048_fea.pdf | Document Posted | In Progress | N/A | N/A | 7/17/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | ||||||||||||||||||||
| AG1-048 | - | Jetersville-Ponton 115 kV | VA | Amelia | Active | Dominion | 106.3 | 106.25 | 52.5 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1048_fea.pdf | Document Posted | N/A | N/A | 7/17/2020 | N/A | N/A | 12/1/2022 | N/A | N | No | |||||||||||||||||||||
| AG1-075 | + | Purdy-Sapony 115 kV | VA | Greensville | Active | Dominion | 150 | 150 | 93.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1075_fea.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 10/15/2024 | N/A | N | No | |||||||||||||||||||||
| AG1-075 | - | Purdy-Sapony 115 kV | VA | Greensville | Withdrawn | Dominion | 150 | 150 | 93.2 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1075_fea.pdf | Document Posted | N/A | N/A | 7/31/2020 | N/A | N/A | 4/13/2021 | 10/15/2024 | N/A | N | No | ||||||||||||||||||||
| AG1-106 | + | Thelma 230 kV | NC | Northhampton | Active | Dominion | 350 | 50 | 34.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1106_fea.pdf | Document Posted | N/A | N/A | 8/28/2020 | N/A | N/A | 6/1/2024 | N/A | N | No | |||||||||||||||||||||
| AG1-106 | - | Thelma 230 kV | NC | Northhampton | Withdrawn | Dominion | 350 | 50 | 34.4 | Capacity | Generation Interconnection | Solar | https://www.pjm.com/pub/planning/project-queues/feas_docs/ag1106_fea.pdf | Document Posted | N/A | N/A | 8/28/2020 | N/A | N/A | 4/13/2021 | 6/1/2024 | N/A | N | No | ||||||||||||||||||||
| AG2-006 | + | Centerburg-Conesville 138 kV | OH | Licking | Active | AEP | 177.5 | 50 | 21 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 10/2/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AG2-006 | - | Centerburg-Conesville 138 kV | OH | Licking | Active | AEP | 200 | 50 | 21 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 10/2/2020 | N/A | N/A | 10/31/2023 | N/A | N | No | ||||||||||||||||||||||
| AH1-031 | + | National-Tangy 138 kV III | OH | Madison | Active | ATSI | 77 | 20 | 8.4 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 6/8/2021 | N/A | N/A | 12/31/2024 | N/A | N | No | ||||||||||||||||||||||
| AH1-033 | + | Sligo Solar | NC | Currituck | Active | Dominion | 19.5 | 19.5 | 13 | Capacity | Generation Interconnection | Solar | In Progress | N/A | N/A | 6/14/2021 | N/A | N/A | 8/15/2024 | N/A | N | No | ||||||||||||||||||||||
| AH1-036 | + | Centerburg 138 kV | OH | Licking | Active | AEP | 277.5 | 100 | 100 | Capacity | Generation Interconnection | Storage | In Progress | N/A | N/A | 6/15/2021 | N/A | N/A | 7/1/2024 | N/A | N | No |