This is a plot of task-days by task name and year within ACD. It appears that after steady improvement, completion times are much better (with many fewer outliers) in 2020.
| TASK_NAME | mean | median | max | sd |
|---|---|---|---|---|
| Intake Form Completed | 1.4 days | 1.0 days | 21 days | 1.6 |
| UFA Completed | 11.7 days | 1.0 days | 225 days | 23.4 |
| Sponsor Reach out | 13.4 days | 4.0 days | 365 days | 32.0 |
| Feasibility w/Documents received | 49.6 days | 9.0 days | 465 days | 81.6 |
| Feasibility approved/CRAO Notified | 30.7 days | 5.0 days | 684 days | 71.4 |
| Request Research Pharmacy Budget | 8.9 days | 1.0 days | 142 days | 18.6 |
| Created CTRF & “Notify ORSP” | 14.3 days | 1.0 days | 530 days | 54.4 |
| Planning Meeting Request Sent | 5.7 days | 1.0 days | 167 days | 13.6 |
| Planning Meeting Completed | 8.8 days | 7.0 days | 99 days | 11.0 |
| IRB Application Submitted | 29.7 days | 7.0 days | 363 days | 60.8 |
| Billing Calendar Received | 15.7 days | 5.0 days | 816 days | 64.8 |
| Care Designations completed | 10.8 days | 2.0 days | 88 days | 17.4 |
| Internal Budget Finished | 10.4 days | 7.0 days | 77 days | 12.7 |
| PI approved Budget | 13.0 days | 2.0 days | 182 days | 25.4 |
| Budget Negotiations | 13.4 days | 2.0 days | 608 days | 54.2 |
| Final Budget | 28.5 days | 10.5 days | 223 days | 42.7 |
| PAF routed | 14.3 days | 5.0 days | 256 days | 26.8 |
| OnCore Budget Build | 30.5 days | 11.0 days | 535 days | 56.2 |
| Calendar Released | 33.8 days | 15.0 days | 773 days | 72.8 |
| PAN Released | 23.2 days | 4.0 days | 280 days | 50.9 |
| Initiate Post-Award Task List | 18.0 days | 1.0 days | 372 days | 46.0 |
| PI Signoff in OnCore | 23.0 days | 5.0 days | 397 days | 46.7 |
| Open to Accrual | 98.0 days | 13.0 days | 7300 days | 632.9 |