Overall Median Days for Each Task

Overall Mean Days for Each Task

Summaries by Task

TASK_NAME mean median max sd
Intake Form Completed 1.4 days 1.0 days 21 days 1.6
UFA Completed 11.7 days 1.0 days 225 days 23.4
Sponsor Reach out 13.4 days 4.0 days 365 days 32.0
Feasibility w/Documents received 49.6 days 9.0 days 465 days 81.6
Feasibility approved/CRAO Notified 30.7 days 5.0 days 684 days 71.4
Request Research Pharmacy Budget 8.9 days 1.0 days 142 days 18.6
Created CTRF & “Notify ORSP” 14.3 days 1.0 days 530 days 54.4
Planning Meeting Request Sent 5.7 days 1.0 days 167 days 13.6
Planning Meeting Completed 8.8 days 7.0 days 99 days 11.0
IRB Application Submitted 29.7 days 7.0 days 363 days 60.8
Billing Calendar Received 15.7 days 5.0 days 816 days 64.8
Care Designations completed 10.8 days 2.0 days 88 days 17.4
Internal Budget Finished 10.4 days 7.0 days 77 days 12.7
PI approved Budget 13.0 days 2.0 days 182 days 25.4
Budget Negotiations 13.4 days 2.0 days 608 days 54.2
Final Budget 28.5 days 10.5 days 223 days 42.7
PAF routed 14.3 days 5.0 days 256 days 26.8
OnCore Budget Build 30.5 days 11.0 days 535 days 56.2
Calendar Released 33.8 days 15.0 days 773 days 72.8
PAN Released 23.2 days 4.0 days 280 days 50.9
Initiate Post-Award Task List 18.0 days 1.0 days 372 days 46.0
PI Signoff in OnCore 23.0 days 5.0 days 397 days 46.7
Open to Accrual 98.0 days 13.0 days 7300 days 632.9