Financial Economics – Week 1, Session 3

NPV Lab: Measuring the Value a Project Adds

Gül Ertan Özgüzer

Session Objectives

By the end of this session, you will be able to:

  • Write and interpret the NPV formula
  • Compute NPV in a spreadsheet three ways: discount factors, NPV(), XNPV()
  • Avoid the classic spreadsheet trap: discounting the year-0 outlay
  • Apply the accept–reject rule to independent and mutually exclusive projects

Warm-up poll

Would you pay $10 million today for $14 million spread over four years?

Vote: Yes · No · It depends on when the money arrives

1 Net Present Value

Independent projects and value additivity

  • A project is economically independent if its net cash flows are not affected by any other project, so it can be judged alone.
  • Value additivity: the values of independent projects add up to the firm’s market value.
  • The useful question: which scale adds the most value? A fleet of 100 trucks could be leased, bought, or bought in stages.

The NPV formula

\[ NPV = \sum_{t=1}^{N} \frac{CF_t}{(1+r)^t} - I \]

Symbol Meaning
\(CF_t\) Net cash flow in year \(t\)
\(I\) Initial investment outlay
\(r\) Required rate of return
\(N\) Project life in years

NPV is the present value of the project’s profit: the increase in firm value if forecasts come true.

The decision rule

If NPV is… The project’s return… Shareholder wealth… Decision
> $0 Beats the required return Increases Accept
< $0 Falls short of it Decreases Reject
= $0 Just equals it Unchanged Indifferent

In a perfect capital market there is no shortage of financing, so every positive-NPV project should be undertaken.

2 Live Demo: Project X

Discount each year, then subtract the outlay

Year Net cash flow Discount factor Present value
1 0 0.9091 0
2 2,000,000 0.8264 1,652,893
3 3,000,000 0.7513 2,253,944
4 9,000,000 0.6830 6,147,121

PV of cash flows = 10,053,958, so NPV = 10,053,958 − 10,000,000 = $53,958. Accept.

Three ways in the spreadsheet

Cash flows in B2:B6 (year 0 in B2), years in A2:A6, rate in E1:

1. Discount factors, then sum

C3:  =1/(1+$E$1)^A3        D3:  =B3*C3        NPV:  =SUM(D3:D6)+B2

2. Built-in function, year 0 added outside

=NPV($E$1, B3:B6) + B2

3. Dated cash flows

=XNPV($E$1, B2:B6, C2:C6)      (dates in C2:C6)

All three give $53,958 for Project X, in Excel and Google Sheets.

The trap: discounting the year-0 outlay

NPV() assumes the first cash flow arrives one period from now. Putting the year-0 outlay inside it discounts it too:

Formula Result
=NPV(10%, B2:B6) 49,053 Wrong: year 0 discounted
=NPV(10%, B3:B6) + B2 53,958 Right

The wrong answer is the true NPV divided by 1.1.

3 Lab 3

Independent or mutually exclusive?

Project Cash flows NPV at 10%
X −10m; 0; 2m; 3m; 9m $53,958
Y −10m; 3.25m a year for 4 years $302,063
  • If independent: accept both, since each increases firm value.
  • If mutually exclusive: accept only Y, the one with the greater NPV.

Your Turn

In the workbook tab “Lab 3 NPV”:

  1. Project Y: compute NPV with discount factors and with NPV(). Bonus: Y is an annuity, so try =PV(10%, 4, -3250000) - 10000000.
  2. Sunrise Coffee (Session 2 cash flows) at 10%: compute NPV and decide.
  3. Remove the $4,000 rent forgone and recompute. What happens to the decision?
  4. Compute Project X’s NPV at 0%, 5%, 10% and 15%.

Debrief: Sunrise Coffee

Case Net cash flows NPV at 10% Decision
With rent forgone (correct) -145,000; 38,875 x 3; 68,875 -1,281 Reject
Rent forgone ignored -145,000; 41,875 x 3; 71,875 8,229 Accept (wrongly)

Ignoring an opportunity cost made a value-destroying project look good.

Preview: NPV depends on the rate

Next week: where this line crosses zero is the IRR.

Wrap-up

Exit check

  1. X and Y are independent and \(r = 10\%\). Which should the firm accept?
  2. What does =NPV(r, CF0:CF4) get wrong?
  3. A project has NPV = $0. What return does it earn?

Glossary of Spreadsheet Functions

Function What it does
=1/(1+r)^t Discount factor for year t
=NPV(rate, values) PV of cash flows starting one period from now; add year 0 outside
=XNPV(rate, values, dates) NPV of cash flows on specific dates; year 0 included
=PV(rate, nper, pmt) PV of an annuity (enter the payment as a negative number)
=SUM(range) Adds up the discounted cash flows

Summary: What We Learned Today

  • NPV = PV of future net cash flows − initial outlay; accept independent projects with NPV > 0.
  • Project X adds $53,958 and Project Y $302,063 at 10%: both if independent, only Y if exclusive.
  • The year-0 outlay is never discounted: the NPV() trap gives $49,053 for X.
  • Ignoring an opportunity cost can turn a bad project into an apparently good one.

Homework: read the textbook on the internal rate of return. Problem Set 1 is due before Session 4.

Reference

Fabozzi, F. J., Neave, E. H., and Zhou, G. (2012). Financial Economics. Hoboken, NJ: John Wiley & Sons.