Why Firms Invest: Capital Budgeting and Owners’ Wealth
| Minutes | Activity | Mode |
|---|---|---|
| 0–5 | Warm-up poll | Poll |
| 5–17 | Capital, capital budgeting, market value rule, risk | Short lecture |
| 17–35 | Activity 1.1: value created or destroyed? | Breakout rooms + R |
| 35–40 | Debrief: rooms post answers in chat | Plenary |
| 40–45 | Exit check and preview of Session 2 | Poll |
A firm earns 12% on a project financed at 10%.
Does the firm’s value rise?
Vote: Yes · No · It depends
A firm’s total assets, tangible and intangible.
Land, buildings, machinery; receivables, securities, patents, copyrights
Additions to the existing capital stock: investment in new assets.
A new plant, a new production line
Assets needed for day-to-day operations that support long-term investments.
Inventory, cash, accounts receivable
Capital budgeting is the process of identifying and selecting investments in long-lived assets: assets expected to produce benefits over more than one year.
Do not change the firm’s course or risk.
e.g., replacing a worn delivery van
Change market position or open new product lines; often large and hard to reverse.
e.g., entering a new product market
A capital project is a set of assets that are contingent on one another and evaluated together.
| Land | + | Facilities | + | Equipment | + | Working capital | = | One project |
|---|
Example: producing a new product requires land, a plant, equipment, and more inventory, cash and receivables.
Management should maximise the market value of the firm, and hence owners’ current wealth.
Firm value today is the present value of all expected future cash flows, discounted at a rate that reflects their risk:
\[ V_0 = \sum_{t=1}^{\infty} \frac{E[CF_t]}{(1+r)^t} \]
In a perfect capital market, investment and financing decisions can be made separately (Chapter 5).
Two cash-flow streams with the same total ($14 million) but different timing, discounted at 10%:
total_early pv_early total_late pv_late
14000000 11471211 14000000 10053958
The later stream is worth about $1.4 million less today: the market value rule cares about when cash arrives, not just how much.
| Sales risk | + | Operating risk | = | Business risk |
|---|---|---|---|---|
| How much output will sell, and at what price | How sensitive operating cash flows are to sales | Priced in the discount rate | ||
| Driven by the economy and the product market | Set by the mix of fixed and variable costs |
The discount rate has one value, two names:
| If the project earns… | Then firm value… | Decision |
|---|---|---|
| More than the cost of capital | Rises | Accept |
| Exactly the cost of capital | Is unchanged | Indifferent |
| Less than the cost of capital | Falls | Reject |
Back to the poll: 12% beats 10% only if 10% is the right rate for the project’s risk. The financing rate is not the hurdle.
Cost of capital = 10% in every case. Work in breakout rooms; post each answer in chat with a one-line reason.
cases <- data.frame(
project = c("Bakery oven", "Utility scrubber", "Retail store"),
project_return = c(0.14, 0.10, 0.07)
)
cost_of_capital <- 0.10
cases$firm_value <- ifelse(cases$project_return > cost_of_capital, "Rises",
ifelse(cases$project_return < cost_of_capital, "Falls",
"Unchanged"))
knitr::kable(cases, col.names = c("Project", "Return", "Firm value"))| Project | Return | Firm value |
|---|---|---|
| Bakery oven | 0.14 | Rises |
| Utility scrubber | 0.10 | Unchanged |
| Retail store | 0.07 | Falls |
Change cost_of_capital to 0.12 and re-run the chunk.
| Function | What it does |
|---|---|
sum() |
Adds up a vector, here discounted cash flows |
x / (1 + r)^t |
Discounts each cash flow (vectorised) |
data.frame() |
Builds a table of cases |
ifelse() |
Applies the value test row by row |
knitr::kable() |
Prints a formatted table |
Homework: read textbook pp. 102–106 and bring one real company announcement of a new investment.