Eko Atlantic City Permit Approval Process — Interactive Flow Diagram showing 5 stages from Preliminary Design Approval to Certificate of Completion

EAC

Eko Atlantic City — Permit Approval Process

Based on PABR Issue 02 (Nov 2024) · CWRR 2025 · Minimum Structural Parameters (Feb 2026)

EACML Official Flow
1
PDA
2
FDA
3
TBP
4
FBP
Certificate
Permit Stages — Click any stage to expand
🏗️

Stage 0 — Land Possession (Prerequisites before any permit)

  • Allocation Paper / Deed of Assignment from South Energyx Nigeria Ltd (SENL)
  • Plot Regulation Sheet (FAR, plot coverage, height limits — specific to your plot)
  • Official Survey Plan (Lagos State Surveyor General)
  • Joint Inspection Report — boundary verification with EACML surveyor
  • Certificate of Survey (Appendix N) — issued by EACML after boundary confirmation
1
PDA
Preliminary Design Approval
₦3,400 /m² land Validity: 1 Year 4 mandatory docs
Required Documents
📐
Concept Design Package (Appendix JJ, Package A) — Site plan, floor plans, all elevations, sections, street schematic elevation, 3D CGI. PDF + DWG, 2 electronic copies, black & white
MAND
📋
Building Information Form (Annex 1 / Fire Req. Sheet) — gross/net areas per use, storeys, floor heights, parking count, FAR calculation
MAND
📝
PDA Application Form — Appendix C (official request, stamped by ARCON-registered architect)
MAND
💳
Fee Receipt — ₦3,400 per m² of land area from EACML treasury
MAND
Review Status Flow
🔵 Submitted 🔶 Under Review 🔶 Design Review ✅ PDA Approved (Appendix D)
↓ if issues
📋 More Info Required 🔄 Resubmitted
Key Compliance Checks at PDA
Setback (Road-side)
≥ 6 m
Setback (All other sides)
≥ 6 m (GF)
Coverage / FAR
Per Lot Reg. Sheet
Fire Resistance (≤18m)
1-hour (R60)
2
FDA
Final Design Approval
₦1,550 /m³ volume Validity: 4 Years 9 mandatory + 4 conditional
Required Documents
📐
Schematic Design Package (Appendix JJ B.1 Arch / B.2 Struct / B.3 MEP+Elec) — 5 A3 hard copies + PDF + DWG, black & white
MAND
🔬
Soil Investigation Report (Appendix L) — signed/stamped by COREN geotechnical engineer + EACML Soil Approval Certificate
MAND
👥
Consultant Appointment Letters (Appendix K) — ARCON/COREN-registered, with Professional Indemnity Insurance
MAND
🔍
Peer Review Reports — Fire Life Safety (Annex 17), Structural, and MEP (Appendix KK) by EACML-approved third-party consultant
MAND
💳
FDA Fee Receipt — ₦1,550/m³ building volume (less PDA deposit already paid)
MAND
📋
FDA Application Form — Appendix E (submitted on completion of detailed schematic design)
MAND
🚗
Traffic Impact Assessment (TIA) — required if parking exceeds 100 cars (PABR §12.7)
COND
🌿
Environmental Impact Assessment (EIA) — required for plots > 50,000 m², petroleum storage, or large educational facilities (PABR §12.8)
COND
🔊
Acoustic Report (PABR Ch.17 / LASEPA 2024) — noise ≤55 dBA day, ≤45 dBA night at plot boundary
COND
🏗️
Shoring Drawings — required if excavation exceeds regulatory depth
COND
🏛️
Architectural Scale Model 1:500 — for display at EAC Sales Office
MAND
Key Structural Parameters (Minimum Structural Parameters 2026)
Design Life
100 Years (S6)
Design Wind (3s gust)
45 m/s
Min Concrete (Piles)
C30/37, SRC
Min Cover (Piles)
75 mm
Chloride Exposure
XS2 / XS3
Fire Struct (>18m)
2-hour (R120)
Review Status Flow
🔵 Submitted 🔶 Under Review 🔍 Peer Review ✅ FDA Approved (Appendix F)
3
TBP
Temporary Building Permit
Included in FDA fee Validity: 2 Years Piling & excavation only
Purpose

TBP authorises piling and shoring/excavation works only. Full superstructure construction is NOT permitted under TBP. Issued while detailed design (FBP drawings) is still being completed.

Required Documents
📝
Structural Engineer Undertaking (Appendix P) — commitment to supervise piling and shoring; stamped by COREN structural engineer
MAND
📋
TBP Application Form — Appendix G (formal request for piling works approval)
MAND
🔬
Non-Working Pile Load Test (PLT) Results — 1 test per 200 piles; load > 2.5× SWL; min 21 days curing before PLT; Mudiame International calibration only
MAND
🔬
Non-Working Pile Integrity Test (PIT) — min 7 days curing. For piles > 25m: Crosshole Sonic Logging (CSL) on 10% of piles instead of PIT
MAND
Key Inspection Triggers (CWRR 2025)
Notice Before Start
7 Days written
Site Engineers
≥1 (or 2 if >5000m²)
Working Hours
07:30–18:30 M–F
Saturday Hours
07:30–16:00 only
Outcome
🔵 Submitted 🔶 Reviewed ✅ TBP Issued (Appendix H)
4
FBP
Final Building Permit
Included in FDA fee Expires with FDA Full construction approved
Purpose

FBP is the final regulatory approval allowing full superstructure construction. All design, structural, and safety requirements must be confirmed before FBP is issued. Requires 100% Design Development (DD) drawings.

Required Documents
📐
Detailed Design (DD) Package (Appendix JJ C.1 Arch / C.2 Struct / C.3 MEP) — 100% construction drawings, PDF + DWG + 2 A2 hard copies
MAND
🏗️
Piling Report — stamped by supervising structural engineer; includes PLT results, PIT results, concrete and rebar test results (CWRR 2025)
MAND
🔬
Working Pile Load Test — 1 per 100 piles of same diameter/depth; load = 150% SWL; settlement < 20mm; rebound > 50%
MAND
🔬
Working Pile Integrity Test results
MAND
📋
Certificate of Completion of Piling and Shoring Works — Appendix R
MAND
👥
Supervising Consultant Appointment Letters (Appendix S) — Architect, Structural, MEP
MAND
📋
FBP Application Form — Appendix I
MAND
🧱
Facade Materials Schedule — full spec for fire (A2-s1,d0 Class) and durability evaluation. Note: Alucobond BANNED >11m; EPS insulation BANNED
MAND
Stage Inspection Points (CWRR 2025)
EACML inspects at: Piling → Foundation → Tanking (waterproofing) → Lintel → Typical slabs & columns → Roofing → Fire/emergency systems commissioning
FINAL
Certificate of Completion & Fitness for Habitation
Per scope Fire Cert: 1 Year renewable 7 prerequisites
Prerequisites (must be completed first)
📋
Certificate of Completion of Piling/Shoring Works — Appendix R
PREREQ
📋
Certificate of Completion of Structural Works — Appendix T (includes Soundness Report, Appendix T1)
PREREQ
📋
Certificate of Plot Demarcation Re-Verification
PREREQ
📝
Request for Structural Works Approval (Appendix T) — structural soundness report from supervising consultant
PREREQ
Documents to Submit
📋
Request for CFH — Appendix U
MAND
Compliance Report — prepared and stamped by ALL supervising consultants confirming compliance with all EACML approvals
MAND
🔥
Fire Safety Report — by approved third-party consultant confirming fire code compliance (triggers Fire Certificate issuance)
MAND
🚧
Permanent Fencing Permit — Appendix GG/HH (fence drawings, survey plan, shoring plan must be submitted separately first)
COND
EACML Final Inspection Verifies
Rentable spaces · Parking provisions · Setbacks · Fire systems · Metering systems · Facade · General compliance · Testing/commissioning of all installed systems
Outcome
📋 Request (App U) 🔍 EACML Inspection 🏆 CFH Issued (App V)
→ After CFH: Apply to EUNL for utility connections (water, power, telecom)

Quick Reference

Eko Atlantic Permit System — PABR Issue 02

Document Types
Mandatory — required for submission acceptance
Conditional — required if threshold is met
Prerequisite — must exist before this stage

⚠️ Critical PABR Prohibitions

  • Boreholes strictly prohibited — use EUNL water supply only
  • Soakaways not permitted — connect to EUNL sewage network
  • Alucobond (ACM) panels banned above 11 m unless proven A2-s1,d0
  • EPS/PSE external insulation banned — use Rockwool or glass wool
  • Wooden/bamboo scaffolding banned — all metallic systems only
  • On-site concrete water addition banned — voids strength guarantee

💰 Fee Summary (PABR Ch. 13)

  • PDA: ₦3,400 per m² of land area
  • FDA/TBP/FBP: ₦1,550 per m³ of building volume (less PDA deposit)
  • Renovation: 25% of prevailing fee, pro-rata to renovation area
  • Modification to FBP: pro-rata to scope of change

📐 Key Regulatory Values

  • Setback (road-side): 6 m minimum (GF & basement)
  • Setback (neighbours): 6 m at GF; 0 m at basement
  • Wind (3-sec gust): 45 m/s, Terrain Cat. 0
  • Noise (day/night): 55 / 45 dBA at plot boundary
  • Min groundwater storage: 2 days capacity
  • PLT for working piles: 1 per 100 piles, 150% SWL
  • Aviation lights: mandatory above 50 m
  • TIA required: parking > 100 cars
  • EIA required: plot area > 50,000 m²

Within-Stage Review Decision

Each stage follows the same internal review loop:

📤 Application Submitted
🔶 Officer — Under Review
Complete & Compliant?
NO ✗
📋 More Info Required
🔄 Applicant Resubmits
↑ loops back to review
YES ✓
✅ Stage Approved
→ Advance to Next Stage
At any point, application may be:
❌ Rejected (fatal deficiency) 🔙 Withdrawn

🏗️ CWRR 2025 — Construction Stage Inspections

After FBP, EACML inspects at mandatory stage notifications:

  • Piling commencement (7 days notice required)
  • Foundation level
  • Tanking / basement waterproofing
  • Lintel level
  • Typical floor slabs & columns
  • Roof structure
  • Fire & emergency systems commissioning
Governing Regulatory Documents
PABR — Planning & Building Regulations
Issue 02 · Nov 2024
CWRR — Construction Works Rules & Regulations
Issue 02 · Aug 2025
Minimum Structural Parameters
Edition 01, Issue 02 · Feb 2026
Code of Practice — Structural Concrete
EACML
LASEPA Environmental Noise Standards
2024
Key Appendices Reference
Appendix A
Lot Regulation Sheet
Appendix C / D
PDA Request / Approval
Appendix E / F
FDA Request / Approval
Appendix G / H
TBP Request / Permit
Appendix I / J
FBP Request / Permit
Appendix JJ
Drawing Package Spec (A/B/C)
Appendix K / L
Consultant Appoint. / Soil Report
Appendix M / N
Survey Request / Certificate
Appendix P
Engineer Undertaking (Piling)
Appendix Q / R / S
PLT / Piling Cert / Appoint.
Appendix T / T1
Structural Works Approval / Cert
Appendix U / V
CFH Request / Certificate
Appendix GG / HH
Fencing Permit Request / Approval
Annex 1 / 17
Building Info Form / FLS Format
Appendix KK
MEP Peer Review Format