Basic Time Series Forecasting Models

##Project Objective

Look at three examples using basic time series forecasting methods.

Question 1: Naive Approach, Part a-d:

a.Most recent value as forecast/Mean Absolute Error?

b.Average all of the data as forecast/Mean Squared Error?

c.Which method is better/Mean Absolute Percentage Error?

d.What is the forecast for week 7?

Step 0: Import the data

weeks <- 1:6
values <- c(17, 13, 15, 11, 17, 14)
ts_data <- data.frame(Week = weeks, Value = values)

Step 1: Most Recent Value as Forecast & Mean Absolute Error

#Most Recent Value as Forecast
forecasts_a <- values[-length(values)] #exclude the last value
actual_a <- values[-1] #exclude the first value
mse_a <- mean((actual_a - forecasts_a)^2)
mse_a #16.2
## [1] 16.2
forecast_week_7_a <- tail(values, 1)
forecast_week_7_a #14
## [1] 14
#Mean Absolute Error
absolute_errors <- abs(forecasts_a - actual_a)
mae <- mean(absolute_errors)
mae
## [1] 3.8

###Step 2: Average all of the data as forecast & Mean Squared Error

#Average of all the data as forecast
cumulative_averages <- cumsum(values[-length(values)]) / (1:(length(values) - 1))
cumulative_averages
## [1] 17.0 15.0 15.0 14.0 14.6
forecasts_b <- cumulative_averages
actual_b <- values[-1] #exclude the first value
mse_b <- mean((actual_b - forecasts_b)^2)
mse_b #8.272
## [1] 8.272
forecast_week_7_b <- tail(values, 1) #average of all weeks as forecast for week 7
forecast_week_7_b #14
## [1] 14
#Mean squared error
naive_forecast <- ts_data$Value[length(ts_data$Value)]
mse <- mean((ts_data$Value - naive_forecast)^2)
mse
## [1] 4.833333

###Step 3: Which method is better & Mean Absolute Percentage Error

#Which method is better
better_method <- ifelse(mse_a < mse_b, "Most Recent Value", "Average of All Data")
list(
  MSE_most_recent_value = mse_a,
  forecast_week_7_a_most_recent = forecast_week_7_a,
  MSE_average_of_all_data = mse_b,
  forecast_week_7_average = forecast_week_7_b,
  Better_Method = better_method
) #Result: Average of all data
## $MSE_most_recent_value
## [1] 16.2
## 
## $forecast_week_7_a_most_recent
## [1] 14
## 
## $MSE_average_of_all_data
## [1] 8.272
## 
## $forecast_week_7_average
## [1] 14
## 
## $Better_Method
## [1] "Average of All Data"
#Mean Absolute Percentage Error
mae_a <- mean(abs(actual_a - forecasts_a))
mae_a
## [1] 3.8

Question 2: Part a & b

a. Construct a time series plot. What type of pattern exists in the data?

b. Compare the three-month moving average approach wth the exponential smoothing forecast using alpha = 0.2. Which provides more accurate forecasts based on MSE?

Step 1: Install & load required libraries

# Set CRAN mirror
options(repos = "https://cloud.r-project.org")

#Install packages
install.packages("dplyr") 
## 
## The downloaded binary packages are in
##  /var/folders/lm/7q9jv5rx5gz0mnz2f3p9v59c0000gn/T//RtmpusjeyX/downloaded_packages
install.packages("zoo")
## 
## The downloaded binary packages are in
##  /var/folders/lm/7q9jv5rx5gz0mnz2f3p9v59c0000gn/T//RtmpusjeyX/downloaded_packages
#Load libraries
library(dplyr)
## 
## Attaching package: 'dplyr'
## The following objects are masked from 'package:stats':
## 
##     filter, lag
## The following objects are masked from 'package:base':
## 
##     intersect, setdiff, setequal, union
library(zoo)
## 
## Attaching package: 'zoo'
## The following objects are masked from 'package:base':
## 
##     as.Date, as.Date.numeric

Step 2: Import the data

df <- data.frame(month=c(1,2,3,4,5,6,7,8,9,10,11,12),
                 data=c(240, 352, 230, 260, 280, 322, 220, 310, 240, 310, 240, 230))

###Step 3: Construct a time series plot

#Part A. Time Series Plot
plot(df$month, df$data, type = "o", col = "red", xlab = "Month", ylab = "Building Contracts",
     main = "Alabama Building Contracts for a 12-month period")

#Interpretation: The time-series plot exhibits a horizontal pattern

###Step 4: Compare the three-month moving average approach wth the exponential smoothing forecast using alpha = 0.2.

#Part B. Three-Month Moving Average
df$avg_contract <- c(NA, NA, NA,
                     (df$data[1] + df$data[2] + df$data[3]) / 3,
                     (df$data[2] + df$data[3] + df$data[4]) / 3,
                     (df$data[3] + df$data[4] + df$data[5]) / 3,
                     (df$data[4] + df$data[5] + df$data[6]) / 3,
                     (df$data[5] + df$data[6] + df$data[7]) / 3,
                     (df$data[6] + df$data[7] + df$data[8]) / 3,
                     (df$data[7] + df$data[8] + df$data[9]) / 3,
                     (df$data[8] + df$data[9] + df$data[10]) / 3,
                     (df$data[9] + df$data[10] + df$data[11]) / 3)

#Calculate the squared errors (only for the months where moving average is available)
df <- df %>%
  mutate(
    squared_error = ifelse(is.na(avg_contract), NA, (data - avg_contract)^2)
  )

#Compute the MSE (excluding the initial months with NA)
mse <- mean(df$squared_error, na.rm = TRUE)
mse #2040.44
## [1] 2040.444
#Exponential Smoothing
alpha = 0.2
exp_smooth <- rep(NA, length(df$data))
exp_smooth[1] <- df$data[1] #Starting point
for(i in 2:length(df$data)) {
  exp_smooth[i] <- alpha * df$data[i-1] + (1 - alpha) * exp_smooth[i-1]
}
mse_exp_smooth <- mean((df$data[2:12] - exp_smooth[2:12])^2)
mse_exp_smooth #2593.76
## [1] 2593.762

###Step 5: Compare MSE

#Compare
better_method <- ifelse(mse < mse_exp_smooth, "Three-Month Moving Average", "Exponential Smoothing")
list(
  MSE_moving_average = mse,
  MSE_exponential_smoothing = mse_exp_smooth,
  Better_Method = better_method
) #Result: Better Method - Three-Month Moving Average
## $MSE_moving_average
## [1] 2040.444
## 
## $MSE_exponential_smoothing
## [1] 2593.762
## 
## $Better_Method
## [1] "Three-Month Moving Average"

Question 3: Part a-c:

##a. Construct a time series plot. What type of pattern exists in the data? ##b. Develop the linear trend equation for this time series ##c. Using the linear trend equation from b, forecast the average interest rate for period 25

Step 1: Install & load required libraries

library(readxl)
library(ggplot2)

Step 2: Import the data

df1 <- read_excel("/Users/ethanma/Desktop/R markdown 2/Mortgage.xlsx")

Step 3: Time Series Plot

#Part A. Time Series Plot
ggplot(df1, aes(x= Year, y = Interest_Rate)) + 
  geom_line() + 
  geom_point() + 
  xlab("Year") +
  ylab("Interest_Rate") + 
  ggtitle("Time Series Plot of Interest Rates for a 30-Year Fixed-Rate Mortgage Over a 20-Year Period")

#Interpretation: We observe a decreasing pattern or trend in the time series plot from 2000 to 2021, 
#followed by an increasing pattern or trend from 2021 to 2023

###Step 4: Linear Trend Equation

#Part B. Develop a Linear Trend Equation
model <- lm(Interest_Rate ~ Period, data = df1)
summary(model)
## 
## Call:
## lm(formula = Interest_Rate ~ Period, data = df1)
## 
## Residuals:
##     Min      1Q  Median      3Q     Max 
## -1.3622 -0.7212 -0.2823  0.5015  3.1847 
## 
## Coefficients:
##             Estimate Std. Error t value Pr(>|t|)    
## (Intercept)  6.69541    0.43776  15.295 3.32e-13 ***
## Period      -0.12890    0.03064  -4.207 0.000364 ***
## ---
## Signif. codes:  0 '***' 0.001 '**' 0.01 '*' 0.05 '.' 0.1 ' ' 1
## 
## Residual standard error: 1.039 on 22 degrees of freedom
## Multiple R-squared:  0.4459, Adjusted R-squared:  0.4207 
## F-statistic:  17.7 on 1 and 22 DF,  p-value: 0.0003637
#Result - linear trend equation: Revenue = 6.7 + (-0.13)*Period OR y = 6.7 + (-0.13)t

#Step 5: Forecast the average interest rate for period 25

#Part C. Forecasat for period 25
forecast_period_25 <- predict(model, newdata = data.frame(Period = 25))
forecast_period_25 #3.47% average interest rate for period 25
##        1 
## 3.472942