The following are necessary steps to create a SVMAQ Document for upload to Aquarius
Part 1 - Fill out site information
Page you open with.
Fill in Information
Blanks to Fill in.
STATION ( Site Number, ie Avery Brook 01171000 )
Station Name - (Auto Fills)
Date
Time ( Time of Arrival at Gage ) ( Don’t change for Daylight vs Non Daylight )
Party ( Initials of all personal present for site visit )
Weather Information
Click on yellow WEATHER button under Party
Blank
Filled out
Photo of Conditions
Comments
Options
Site Visit = ( Tape Down, Control Inspection )
QM = ( Flow Measurement )
GHZF = ( Gage Height at Zero Flow )
CSG = ( Crest Stage Gage - Bucket Test, and Read )
Levels = Level Set Done
Camera Download = ( FPE camera was downloaded. )
Comment on anything that will be valuable to an accurate discharge monitoring.
Tree blocking control.
Gage fallen.
Save File
Click File then Save As…
File Gets Saved .
Site Number ( 01171000 )
Date ( 20220604 )
Start Time ( 102900 )
Site Visit Tasks
- Click on Button in bottom right of screen SITE VISIT TASKS
- Options
GZF Inspection - Gage Height at Zero Flow
Control Inspection - Where you enter weather the control is blocked.
Sensor Inspections - Put your Stage readings in whether it be from a reference point or a real time sensor.
- CSG Data will go in here.
Station Levels - Both where levels are entered and all RP and RM values are stored.
Discharge Measurement - Where both flow tracker files is stored and any information corresponding to the sensor.
- Tip
- To get into any tab just click on yellow box.
Part 2 Data Entry
Control Inspection
- Blank
- Filled
Options
Control Type ( Section, Channel , Combined chan/sect )
Section
Channel